B
Barbara G
Hi,
When I view the Timesheet Audit All report in the Report Pack 2007, my hours
are showing incorrectly. For training purposes, I have recalled my timesheet
and the hours are accumulating instead of replacing them. For example, I had
a 40 hour week timesheet and I recalled it. I then re-submitted and
re-imported it. Now, this report is showing 80 hours instead of 40 hours for
that week. I am the Project Server administrator and I have verified Data
Analysis is showing the correct information. I'm wondering if I'm using the
wrong field for the report. Will you please tell me what field, table and
database I should be using?
When I view the Timesheet Audit All report in the Report Pack 2007, my hours
are showing incorrectly. For training purposes, I have recalled my timesheet
and the hours are accumulating instead of replacing them. For example, I had
a 40 hour week timesheet and I recalled it. I then re-submitted and
re-imported it. Now, this report is showing 80 hours instead of 40 hours for
that week. I am the Project Server administrator and I have verified Data
Analysis is showing the correct information. I'm wondering if I'm using the
wrong field for the report. Will you please tell me what field, table and
database I should be using?