Project Server Resource Question

Joined
Mar 25, 2013
Messages
1
Reaction score
0
We're migrating our schedules to Project Server 2010 and have several tasks with multiple resources assigned to them.

If 4 people are assigned to a task, and two people gave updates, and we know the task is completed, is there an easy way for us to mark those last two assignments as finished? In the Approval Center, can the approver update the task level % complete or task level remaining hours (i.e. set to 0h) or task level actual finish?
 