Hi Project Server Experts,

I am administering a new Project Server 2007 environment at our
company and would like some help on the following issues.

1.
After the projectmanager has approved the tasksupdates of his
resources, the tasksupdates are not yet in the published database.
Another action is needed. Can I automate this last step? So after
approving the tasks updates will be automatically integrated in the
projectplan.

2.
When my resources have updated their tasks, meaning have updated their
'actual work' and 'remaining work' the projectmanager can see these
values when approving this task updates. But I want some more
information displayed. I would also like to see the difference in
hours between the last update and the current update. e.g. the
remaining work has increased from 2 days to 7 days, meaning an
increase of 5 days! Oops :) Is it possible to show this value of 5 in
a field at the update sheet?

3.
I want my resources to manually create tasks in activity plans and
make it possible to write hours on this tasks in their timesheet
without(!) the projectmanager first having to approve this tasks.
Where and what do I need to configure to establish this?

4.
In the data analysis I have some measurements and some facts depending
on the cube I have chosen. A fact may be the hours of work. Can I also
display dates (deadlines in my case) in the area where normaly the
facts are displayed.



Hope my questions are clear and you can help me. If you need more
information, please let me know.

Best regards,
Henk
 