Hi - hope someone out there can help us here.

We are implementing Project Server and understand how resources can report
hours worked against projects using PWA however we would like to use this
method as a complete time sheet system so how can i configure it to account
for hours spent on non project activities eg admin or holidays etc?

Eternally greatful for an answer!

Regards
 
S

Shahid

Hi Chris

Create Administrative Projects and ask team members to book time against
those Administrative projects. For help on Administrative Projects, look in
MS project onilne help.