R
Ramesh
Hi,
We have recently implemented microsoft project server 2003 in our
oragnisation.
My projects team is facing big issuse in project server, ie whenever a
resource submit his timesheet (effort) in project web access approved by the
project manager, this will be updating the actuals in microsoft project plan
in the server, the problem is the plan effort is also changing to actual
effort.
For Example the resource A has planned effort of 4 hrs, but the resources
complete the task within 3 hrs and sent for manager approval. When the
manager approve the time sheet. The planned effort of 4 hrs is changed to 3
hrs.
Please hlep me on the above issuse
Thanks in advance
Regards,
Ramesh
We have recently implemented microsoft project server 2003 in our
oragnisation.
My projects team is facing big issuse in project server, ie whenever a
resource submit his timesheet (effort) in project web access approved by the
project manager, this will be updating the actuals in microsoft project plan
in the server, the problem is the plan effort is also changing to actual
effort.
For Example the resource A has planned effort of 4 hrs, but the resources
complete the task within 3 hrs and sent for manager approval. When the
manager approve the time sheet. The planned effort of 4 hrs is changed to 3
hrs.
Please hlep me on the above issuse
Thanks in advance
Regards,
Ramesh