Project should have an colour coding option for task status

M

Matt Atkinson

My work community prefer a report of project progress in the format of a RAG
(Red-Amber-Green) status. I currently have to copy and paste in into Excel
to do this and have set up a macro to automate the process as much as
possible. I know a lot of IT professionals who use this format and get great
customer feedback and therefore I think it would be beneficial to have an
option in Project to publish a RAG report rather than having to export to
Excel. (I would be happy to send my example if it helps)
 
J

Jan De Messemaeker

Hi,

1. The only way to use a number of Text Colours is through a VBA macro
2. Background colors are not available.
HTH
 
J

JulieS

Hi Matt,

If your work community would be satisfied with Gantt Bars in the RAG status
see:

www.mvps.org/project FAQ #31 for some ideas about customizing Gantt bars
based upon the flag fields.

If you would like to see Graphic indicators for RAG status as part of a
table see Mike Glen's article at:

http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=403

His example uses graphic indicators for cost but you can modify the custom
field to show variance for the Start or Finish fields.

Hope this helps. Let us know how you get along.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top