GlenA
Hi, I'm using Project to model some things that will happen within the scop
of about 2 hours (I'm trying to make the project 2 hours long). I have the
Duration in minutes figured out and the Timescale in minutes figured out.
But I want to
1) Make a task that will, for example, start at 23 minutes and end at 33
minutes. The Start and End fields only allow dates. Is there a way to do
this or some other strategy? Setting "Work is entered in" to minutes under
Options->Schedule did not help.
And 2) I want to set the Project time to be a total of 2 hours.
of about 2 hours (I'm trying to make the project 2 hours long). I have the
Duration in minutes figured out and the Timescale in minutes figured out.
But I want to
1) Make a task that will, for example, start at 23 minutes and end at 33
minutes. The Start and End fields only allow dates. Is there a way to do
this or some other strategy? Setting "Work is entered in" to minutes under
Options->Schedule did not help.
And 2) I want to set the Project time to be a total of 2 hours.