Q
quantum
Problem with Microsoft Project 2003 is that, like its predecessors, the
programme start date cannot be altered to update all tasks by one single
entry unless all tasks are artificially linked.
Often a gantt chart will be written as a draft, or initial, arrangement with
the actual start being changed and occuring somewhat later. Using baseline
only leads to confusion once the project starts and reporting progress ensues.
Any chance of a solution?
programme start date cannot be altered to update all tasks by one single
entry unless all tasks are artificially linked.
Often a gantt chart will be written as a draft, or initial, arrangement with
the actual start being changed and occuring somewhat later. Using baseline
only leads to confusion once the project starts and reporting progress ensues.
Any chance of a solution?