Project Start Date Changes to so much early

A

annisa18

Hi,

I was working with Microsoft Project yesterday. I was originall
maintaining the project file manually. But now that we have a server,
was preparing my file to be uploaded. I erased all my resources ther
(because I will reassign resources created in the server once the fil
gets uploaded).

As I was erasing the resources in my project file, things change t
those tasks which have been tracked.

There are some tasks whose start date changed to so much earlier like
1/6/84.

My project time range is only year of 2010.
Some tasks finish date also changes to unreasonable time.

And some of the % tracking becomes 0%, which it was originally marke
complete.

Will you help me understand what happens when one erases resources i
the project file?

I was trying to use the Replace - option in the Server, but it wasn
working properly at that time.

Thanks,
Annis
 

Ask a Question