Project Status Date

Joined
Dec 18, 2019
Messages
3
Reaction score
0
Is there a way to make a Custom Field show the Project Status Date? I am using Project 2016 Standard. Thanks for any insight.
 
Joined
Oct 24, 2021
Messages
1
Reaction score
1
Hi John,

Yes, you can use a date custom field like Date1. Then customized it by adding a formula that only requires "Status Date". Make sure to mark that summary tasks should use the formula. Then you should get the status date in custom field Date1.