P
Pratta
Hi Deluth
What you want is what project does best.
If you are having poblems it may be because you are not
allowing Project to control the flow. Make sure that all
tsks are "as soon as possible" - with no hard coded dates.
Select each task or network of tasks and with the Tracking
toolbar select "update as scheduled" or with % completes
(as required) and then for those tasks not complete/partly
complete selected, select "re-schedule tasks".
Project will then do its work. Can also use filters/views
to help.
Baselining the schedule will also help, and depicting the
baselined dates in the bar-styles.
The Resource-Ussage view will give you a good view of what
remains/ has been done by task and resource.
I suggest you also insert a current date line into your
gantt to assist. Do this by right clicking in the gantt,
select grid-lines/ current date and select the format.
The gantt will then clearly show on the left of the line,
what should have been completed, and on its right, the
tasks that need to be completed.
Hope this is what you were after.
Regards.........Geoff Pratt
done serially. The tasks are dependent on scheduling the
resource time, not necessarily by true dependencies of the
tasks. Sometimes there would be 3 or 4 tasks at 40-50%
done. What I would like to get from Project is a general
status of all the tasks, taking in account the unfinished
tasks as well as the % complete of all the dependencies
for the milestone.
left. Overall, this resource would be on time since there
are 4 days left until the milestone date and the resource
has 4 days left of work. I did this calculation by hand,
but is there a way Project can calculate something like
this? What would really help would be for Project to let
me know if the milestone is at risk due to the dependent
tasks not completing in time.
What you want is what project does best.
If you are having poblems it may be because you are not
allowing Project to control the flow. Make sure that all
tsks are "as soon as possible" - with no hard coded dates.
Select each task or network of tasks and with the Tracking
toolbar select "update as scheduled" or with % completes
(as required) and then for those tasks not complete/partly
complete selected, select "re-schedule tasks".
Project will then do its work. Can also use filters/views
to help.
Baselining the schedule will also help, and depicting the
baselined dates in the bar-styles.
The Resource-Ussage view will give you a good view of what
remains/ has been done by task and resource.
I suggest you also insert a current date line into your
gantt to assist. Do this by right clicking in the gantt,
select grid-lines/ current date and select the format.
The gantt will then clearly show on the left of the line,
what should have been completed, and on its right, the
tasks that need to be completed.
Hope this is what you were after.
Regards.........Geoff Pratt
tracking their progress and sometimes, the tasks are not-----Original Message-----
Hi - the project I'm working on has 20+ resources. I'm
done serially. The tasks are dependent on scheduling the
resource time, not necessarily by true dependencies of the
tasks. Sometimes there would be 3 or 4 tasks at 40-50%
done. What I would like to get from Project is a general
status of all the tasks, taking in account the unfinished
tasks as well as the % complete of all the dependencies
for the milestone.
75% done with 2 days left, task 3 - 50% done with 1 dayFor example: task 1 - 50% done with 1 day left, task2 -
left. Overall, this resource would be on time since there
are 4 days left until the milestone date and the resource
has 4 days left of work. I did this calculation by hand,
but is there a way Project can calculate something like
this? What would really help would be for Project to let
me know if the milestone is at risk due to the dependent
tasks not completing in time.