Project stays checked out from EPM server

S

Spunky

When I edit and save a project it stays checked out and I have to go in under
administrator and check it back in. This does not happen all the time and
does not happen with all the projects. I thought I needed a reinstall of MS
Project but then one other person had this problem with one project. I tried
the same project and it stays checked out with me. I've just began to
trouble shoot this but one thing I have found is when I add a copy of an
email (copy/paste) into the notes, save and close, this project stays checked
out. It is not necessiarly notes specific though it happens every time with
notes and most of the time with other changes. Perhaps it a corrupt project,
however I have had at least three projects checked out to me at a time when
I've only opened, modified, and closed them. All projects do not stay
checked out when I open, edit, save and close them.
 