C
Chilvers
I have a 57 day project and I marked the first task 100% complete. It is a
2-day task completed on 2 days. On the Tracking Table, why does my Project
Summary show Actual Duration 2.07 and Duration Remaining 54.93 rather than
Actual Duration 2 and Duration Remaining 55
2-day task completed on 2 days. On the Tracking Table, why does my Project
Summary show Actual Duration 2.07 and Duration Remaining 54.93 rather than
Actual Duration 2 and Duration Remaining 55