V
Vinayak Bhat
Initially I was getting the tasks duration in fractions.
Then I have set the tools-->options and calendar duration properly.
Although it has been corrected at the task level the project summary is
still showing in fraction. How do I correct them
thanks very much in advance.
Vinayak Bhat
Then I have set the tools-->options and calendar duration properly.
Although it has been corrected at the task level the project summary is
still showing in fraction. How do I correct them
thanks very much in advance.
Vinayak Bhat