project summary task---Urgent! please
Hello!
The poject summary task of my project plan is wrong.
0 Project name.published 0 days 9/1/2004 9/1/2004
1 Project name (summary task) 237 days 9/1/2004 6/30/2005
2 initiation 237 days 9/1/2004
6/30/2005
My question why the project name.published is 0 days it should be 237 days
and end date should be 6/30/2005
Your help is greatly appreciated!
Thanks!
Sankar,PMP
The poject summary task of my project plan is wrong.
0 Project name.published 0 days 9/1/2004 9/1/2004
1 Project name (summary task) 237 days 9/1/2004 6/30/2005
2 initiation 237 days 9/1/2004
6/30/2005
My question why the project name.published is 0 days it should be 237 days
and end date should be 6/30/2005
Your help is greatly appreciated!
Thanks!
Sankar,PMP