R
roberta
I have inserted via the 0ptions menu a project summary
task and I have now started tracking my project. I have
completed 100% the first three tasks which total 8 days
(al of which started on time and were completed in the
baseline duration times. The associated summary says 8
days but my project summary only shows 5.36 days?
There are no overlaps, calendar constraints, contouring or
anything involved.
Can anyone explain, please, how this is being calculated?
task and I have now started tracking my project. I have
completed 100% the first three tasks which total 8 days
(al of which started on time and were completed in the
baseline duration times. The associated summary says 8
days but my project summary only shows 5.36 days?
There are no overlaps, calendar constraints, contouring or
anything involved.
Can anyone explain, please, how this is being calculated?