J
JosieMarley
We've recently upgraded to project server 2007 and I'm trying to create a
project view that displays the Unique ID for each task. As this field is not
one avaiable when creating a new project view I decided to use a formula in
the task field Number 1, setting it to [Unique ID]. The field looks correct
when I view it in Project Professional however after publishing the project
and then looking at it from the web access project view, although the Number
1 field appears it is not populated. I've previously used Enterprise task
fields and these appear no problem, it's just the project task fields that
don't seem to work. Any suggestions as to what I'm doing wrong? I've tried
re-publishing the schedule. I thought perhaps the fact that it was a formula
was a problem so I simply then copied the contents of the Unique ID field
into another task field Number 2. This doesn't work either. Any help would
be very welcome!
project view that displays the Unique ID for each task. As this field is not
one avaiable when creating a new project view I decided to use a formula in
the task field Number 1, setting it to [Unique ID]. The field looks correct
when I view it in Project Professional however after publishing the project
and then looking at it from the web access project view, although the Number
1 field appears it is not populated. I've previously used Enterprise task
fields and these appear no problem, it's just the project task fields that
don't seem to work. Any suggestions as to what I'm doing wrong? I've tried
re-publishing the schedule. I thought perhaps the fact that it was a formula
was a problem so I simply then copied the contents of the Unique ID field
into another task field Number 2. This doesn't work either. Any help would
be very welcome!