Hi,

We are using project server SP2 with project 2003.

We are having problems with the project client not completely synchronizing
with the project server.

Example - We deleted tasks from a user - they are not closing out in project
server, they still appear active (without the X in front of them)

Example - We finish tasks in project client (mark 100% complete) they are
not updating in project server (still showing resource has time to spend
against task)

Any suggestions would be appreciated as I have a big mess on my hands trying
to get these two systems to tick/tie.

Thanks a bunch!

Kebin Brezina
 
D

Dale Howard [MVP]

Kevin --

Do you click Collaborate - Publish - All Information after each update
cycle?
 
K

Kevinb

Yes, we have consistently seen errors since the original install. Here's
some of the examples.

Most seen error:

Event ID 2
User: NT Authority\local service

Component: PjMsgHlr
File: C:\Office\devsp\project\WebClient\source\server\pjmsghlr\updatedb.cpp
Line: 676
Error Number: 0x8c040012
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>

Additional Errors:

Component: PjSvrNPE
File: C:\Office\devsp\project\WebClient\source\server\pjnpe\emailhelper.cpp
Line: 217
Error Number: 0x8004020f
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>
 
D

Dale Howard [MVP]

Kevinb --

Thanks for the info. Would you please repost your original message, along
with the Application Event Log errors, so that our technical folks can
diagnose and solve your problems? Thanks!

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the books on Project Server"


Kevinb said:
Yes, we have consistently seen errors since the original install. Here's
some of the examples.

Most seen error:

Event ID 2
User: NT Authority\local service

Component: PjMsgHlr
File:
C:\Office\devsp\project\WebClient\source\server\pjmsghlr\updatedb.cpp
Line: 676
Error Number: 0x8c040012
Description: <Description><![CDATA[Assert Detected. The error code was
also
included.]]></Description>

Additional Errors:

Component: PjSvrNPE
File:
C:\Office\devsp\project\WebClient\source\server\pjnpe\emailhelper.cpp
Line: 217
Error Number: 0x8004020f
Description: <Description><![CDATA[Assert Detected. The error code was
also
included.]]></Description>




Dale Howard said:
Kevinb --

Are you seeing errors in the server's Application Event Log?
 
F

FaisalM

First make sure your Project Server & Project Professional are current with
Service Pack level.

Project Server = SP2a
Project Professional = SP2

Try these KB articles:
http://tinyurl.com/adyap

I've seen the similar issue you mentioned in your example 1. I deleted those
assignments from the DB & that removed those from appearing in user's
timesheet.

--
FaisalM
http://www.FaisalMasood.com/

My Project Blog
http://www.faisalmasood.com/blog/msproject

My Sharepoint Blog
http://www.faisalmasood.com/blog/sharepoint
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top