Project Task Updates

C

Craig Smillie

Does anyone know how I can find out any chamges to the finishd dates within
my projects. I have projects that many people can update, and I need to find
a quick way to see if anyone has extended durations, finish dates etc.

Any help appreciated

thanks
 
R

Rob Schneider

Craig,

Kind of an open-ended question with lots of possibilities which may or
may not be appropriate for your situation (which from the information
you provide I can only imagine).

Some random thoughts in no particular order (except for the first which
I deem essential):

: make a team rule that any changes the result in changed finished dates
(or other things you care about) must be informed to you by the person
making the change. (If they don't inform you, you remove their rights to
the file to make changes). Even if you cannot enforce this automation
(practically), IMHO the people involved in the project must have this
attitude.

: remember it is normal (and desired) for Project to recompute project
end dates as the project progresses. You *want* Project to give you an
indication of the current forecast on end date, which can and should
change on every update of the plan. (If you have hard-coded finish dates
on tasks then Project isn't being used as it is intended to be used).

: ensure the plan is baselined so you can remember the basis you are
trying to compare to. (However, people who have access to the file can
change these baselines should they be so inclined ... reinforces the
need for the first item).

: remember it is hard/impossible to lock down the contents of anything
in the MPP file. Once opened, anybody can change anything. The only
control you have is granting access to the file to a) get it, and b) put
it back (via email, file shares, document management check in/out
process, whatever ...). The key control risk is having the permissions
to put the file back into the "official" place for re-use by others with
the possiblity of a "wrong" change becomes "right" simply by being
published.

: Project provides a handy field called Deadline. Put deadlines on key
milestones on tasks that you want to watch. As long as recomputed
finish dates are within the deadline, do you really need to immediately
know that a change to the plan occurred.

There are surely other things to consider that are perhaps more relevant
to your team and organisation.

--rms

www.rmschneider.com
 
J

Jim Aksel

I can add two items to Rob's excellent post. First, as he said, it is
essential to set a baseline and properly maintain the schedule wit remaining
work and remaining duration.

An additional feature is the Project Compare Utility located here:
View/Toolbars/Compare Project Versions... The tool is a little tempermental
but does work very well if you keep two things in mind:

1. When you compare two files, they must both trace back to a common
ancestor file. This is normally just an older version of the same file (May
vs June) etc.

2. There must be a common table in the two files to compare. I usually
create a table called "Compare" and specify all the variables (fields) I want
to compare in that new table.

To keep the tool running well, you need to adopt some practices. That is,
do not delete a task and retype the same task elswhere. Instead use
drag/drop to move tasks.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
V

vanita

Hi

You may follow these steps:
1. Before the first update save the Baseline
2. Before the second update save latest Start/Finish dates as Start1/Finish1
dates through Tools > Tracking > Set baseline
3. Let your team members update the schedule as required and this will
update Start/Finish dates in your schedule
4. To view the changes made in this update you may insert columns for
Start1/Finish1 or for graphical comparison insert bars for Start1/Finish1 in
2nd row through Format > Bar styles. If you make these changes in Tracking
Gantt view at any point of time you will view latest schedule, last updates
schedule and baseline schedule all together for comparison.
5. You may save Start/Finish dates upto last 10 updates and in the Gantt
chart view you may go upto 4 rows.

I hope it helps.
Vanita
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top