R
Ray Powers
I have a project called Router Configuration. This project had roughly 15
tasks (small project) while in discovery. During elaboration, we reorganized
the project plan, deleted most of the tasks, and created a new task list
under the new ideas. We had published the first version. When we were ready,
we published the project again, deleting all the old tasks. A month went by
and we successfully completed the project, setting it to 100%.
Now, three weeks after the project has been 100% complete, some of the tasks
from the original task list are beginning to show up on people's task list,
as 0% complete. For example someone has a task of "re-cable for new router"
at 0%, over due by two months, when that task no longer even exists. If I
open the project in Microsoft project, the task is not there, and I never
saved a baseline since the project was so short.
Publishing the project yet again did nothing, nor did Republishing
assignments.
My simple question is what is the best way to get rid of these? I resorted
to having the individuals "re-complete" them in their timesheet and resubmit
them. I accepted the updates and the server tried to update the tasks, but of
course could not since they no longer existed. It gave an error, but hey, the
tasks were gone for those people. But I am not sure this is the best method.
The more important question, however, is what would cause this to begin
with? It looks like some form of synchronization issue between the actual
projects and the task lists, but I have no idea what would cause it and how
to prevent it. Needless to say this is causing us a lot of concern about the
validity of the data we are getting from Project, so I'd like to solve it
immediately and have a reason for it.
Thanks in advance for any help!
Ray
tasks (small project) while in discovery. During elaboration, we reorganized
the project plan, deleted most of the tasks, and created a new task list
under the new ideas. We had published the first version. When we were ready,
we published the project again, deleting all the old tasks. A month went by
and we successfully completed the project, setting it to 100%.
Now, three weeks after the project has been 100% complete, some of the tasks
from the original task list are beginning to show up on people's task list,
as 0% complete. For example someone has a task of "re-cable for new router"
at 0%, over due by two months, when that task no longer even exists. If I
open the project in Microsoft project, the task is not there, and I never
saved a baseline since the project was so short.
Publishing the project yet again did nothing, nor did Republishing
assignments.
My simple question is what is the best way to get rid of these? I resorted
to having the individuals "re-complete" them in their timesheet and resubmit
them. I accepted the updates and the server tried to update the tasks, but of
course could not since they no longer existed. It gave an error, but hey, the
tasks were gone for those people. But I am not sure this is the best method.
The more important question, however, is what would cause this to begin
with? It looks like some form of synchronization issue between the actual
projects and the task lists, but I have no idea what would cause it and how
to prevent it. Needless to say this is causing us a lot of concern about the
validity of the data we are getting from Project, so I'd like to solve it
immediately and have a reason for it.
Thanks in advance for any help!
Ray