Project Tasks not appearing in PWA

J

Jillian

Recently 4 seperate projects (out of about 50) have been experiencing a
problem where resources assigned to tasks have been able to see their tasks
in PWA but over the past week the tasks have been removed from PWA and the
project is not visible at all. Any suggestions? (We have already tried
republishing and assigning.)
 
D

Dale Howard [MVP]

Jillian --

In the future, please let us know what version of Project Server you are
using. 2002, 2003, or 2007? The answer to your question really depends on
what version you are using. If you are using Project Server 2002, 2003, or
2007, here's one thing that the PMs of the four projects can do to
troubleshoot the problem:

1. Open one of the four projects in question.
2. Click Tools - Build Team from Enterprise.
3. Make sure that all of the human enterprise resources have their Booking
type set to Committed.
4. Click OK.
5. If the you found Proposed resources in step #3 and set them to
Committed, save and publish the project.

If you are using Project Server 2007, then the PMs of the four projects can
also try the following:

1. 1. Open one of the four projects in question.
2. Apply the Gantt Chart view.
3. Right-click on the Duration column header and select the Insert Column
item from the shortcut menu.
4. In the Column Definition dialog, select the Published field and click
the OK button.
5. Make sure the Published field value is set to Yes for every task to
which resources are assigned (ignore summary tasks and milestone tasks).
6. If you changed the Published value to Yes for any task, save and publish
the project.

Let us know if this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top