H
HQ
I am working on establishing a schedule for an audit engagement. The issue i
have is with the existence of high level tasks that have no dependencies but
sub-tasks within those high level tasks that do have dependencies within
themselves. For example lets take a testing cash task (summary task) and a
testing inventory task (Summary Task). These tasks have absolutely no
relationship. They have sub-tasks, such as peform testing, manager review,
addressing review notes . These sub-task have a FS dependency with each other
within the applicable summary task but the high level task of testing cash
has no dependency with testing inventory. They can occurr simultaenously.
What if the same resource is assigned to complete the perform testing
sub-task within the two summary tasks with no dependencies? I would like the
resource to work 100% on one of these tasks at a time until completion. These
tasks do have different priorities. For example i would like the resource to
work on testing inventory first and than on cash. How can i achieve that
without creating any dependencies?
Also in our field a testing task is rarely completed without any
interruptions. SO if my resource is working on inventory and comes across any
delays such as client delays, i would like the resource to start working on
cash until they can start again on inventory. How can i achieve this kind of
flexibility so that i can change the baseline schedule for appropriate
comparison with actual work and its impact on project finish date.
Also do i have to enter the subtasks of manager review and addressing review
notes for every summary task. Can i enter them once and link them in such a
way that as soon as any of the sumary tasks are complete they are immediately
ready for review?
have is with the existence of high level tasks that have no dependencies but
sub-tasks within those high level tasks that do have dependencies within
themselves. For example lets take a testing cash task (summary task) and a
testing inventory task (Summary Task). These tasks have absolutely no
relationship. They have sub-tasks, such as peform testing, manager review,
addressing review notes . These sub-task have a FS dependency with each other
within the applicable summary task but the high level task of testing cash
has no dependency with testing inventory. They can occurr simultaenously.
What if the same resource is assigned to complete the perform testing
sub-task within the two summary tasks with no dependencies? I would like the
resource to work 100% on one of these tasks at a time until completion. These
tasks do have different priorities. For example i would like the resource to
work on testing inventory first and than on cash. How can i achieve that
without creating any dependencies?
Also in our field a testing task is rarely completed without any
interruptions. SO if my resource is working on inventory and comes across any
delays such as client delays, i would like the resource to start working on
cash until they can start again on inventory. How can i achieve this kind of
flexibility so that i can change the baseline schedule for appropriate
comparison with actual work and its impact on project finish date.
Also do i have to enter the subtasks of manager review and addressing review
notes for every summary task. Can i enter them once and link them in such a
way that as soon as any of the sumary tasks are complete they are immediately
ready for review?