Project team member receiving pop-up you do not have Create ObjectLink Permission when trying to lin

K

kix1956

User is assigned to the Team Member group as far as permissions go and
is unable to link a document to a task, getting a pop-up indicating
that he lacks the Create Object Links Permission. Where can this
permission be found and manipulated in Project 2007?
 
C

Chak

Hello kix1956,

It's category permission. Please see the security categories
associated with that group. I believe it is My Tasks category. Please
select "Create Object Links" permissions.

Thanks
Chak
http://www.epmcentral.com
 