Hello All.

I'm a new user to Project. Currently, working on developing a template that
can be applied to re-curring projects. It appears that I always have to
enter a start from date, or rather, Project enters one for me. Is there any
way to alter that in my template?

Thanks for your time!!
 
D

Dale Howard [MVP]

Jules --

The Start date in the template is the "generic" start date for the project.
When a project manager creates a new project from your template, he/she will
need to click Project - Project Information and set the Start date for their
project. That's just the way the system works. Make this a training and
performance issue for your project managers, and I think they will do fine.
Hope this helps.
 