Project Timesheet Reporting

N

newbie2

I asked another project manager to add tasks to one of my existing enterprise projects. When my team reported their time thru pwa their updates went to her for acceptance instead of me. Why? and How can I change it so they come to me?
 
S

Sean

Whoever creates and publishes assignments or assignment
changes will become the assignment owner, and PWA will
route updates accordingly. You can easily make yourself
the owner of the assignments by going Collaborate,
Publish, Republish Assignments. On the Republish
Assignments dialog box select "become the manager for
these assignments." Now PWA will route updates through
you!

Hope this helps!

----------------------
Sean Pales
EPM Solutions Group
Bennett Adelson
www.bennettadelson.com
-----Original Message-----
I asked another project manager to add tasks to one of
my existing enterprise projects. When my team reported
their time thru pwa their updates went to her for
acceptance instead of me. Why? and How can I change it so
they come to me?
 
N

newbie2

Thank you. That worked.
-----Original Message-----

Whoever creates and publishes assignments or assignment
changes will become the assignment owner, and PWA will
route updates accordingly. You can easily make yourself
the owner of the assignments by going Collaborate,
Publish, Republish Assignments. On the Republish
Assignments dialog box select "become the manager for
these assignments." Now PWA will route updates through
you!

Hope this helps!

----------------------
Sean Pales
EPM Solutions Group
Bennett Adelson
www.bennettadelson.com

my existing enterprise projects. When my team reported
their time thru pwa their updates went to her for
acceptance instead of me. Why? and How can I change it so
they come to me?
.
 