Project TimeSheet

S

sw

Has anyone experienced the following:

One of my resources entered time to a project in March.
However, the time should have been allocated to a
different project for the month of March. He went back to
March to zero out the hours to the first project and put
them in the appropriate project. When he saved the data
and clicked 'Update All'.....all of the transferred data
did not transfer over to the new project. Two weeks
updated accurately and the other two weeks worth of data
reverted back to the original project.

Any ideas?
 