J
John Horton
(As suggested by Gary L. Chefetz in another thread)
To achieve something like Give Gets I am considering creating a Milestone
schedule that is populated by links to milestones in all the other files in
my instance. I have mocked it up and it works exactly the way I want it to.
What worries me is that in time I could have a thousand links between
projects. Will all these project-to-project links be a problem for the data
base?!?! Within the database do the project-to-project links require more
resources then links within a project.
I am prepared for the links file to be slow to open.
I looked at deliverables and do not think it works for my user base. SRS
reports are out if the question as we do not have an in-house programmer.
To achieve something like Give Gets I am considering creating a Milestone
schedule that is populated by links to milestones in all the other files in
my instance. I have mocked it up and it works exactly the way I want it to.
What worries me is that in time I could have a thousand links between
projects. Will all these project-to-project links be a problem for the data
base?!?! Within the database do the project-to-project links require more
resources then links within a project.
I am prepared for the links file to be slow to open.
I looked at deliverables and do not think it works for my user base. SRS
reports are out if the question as we do not have an in-house programmer.