I am new to MS Project Server and Share Point Services. I have a requirement
to track the various events and timeline of constrcution activities. I can
create tasks and activities on MS Project . But I have different check lists
and forms ( excel and word) associated with most of the activities. Assigned
user(s) would update this documents over web. Finally I should be able to
build report based on information collected on how long each effort took and
the summary from check list. IS it possible to these using MS Project server
and MS SharePoint services. Where will I get details to get started. Please
advice.

Thanks

Jibu
 
J

John

Jik said:
I am new to MS Project Server and Share Point Services. I have a requirement
to track the various events and timeline of constrcution activities. I can
create tasks and activities on MS Project . But I have different check lists
and forms ( excel and word) associated with most of the activities. Assigned
user(s) would update this documents over web. Finally I should be able to
build report based on information collected on how long each effort took and
the summary from check list. IS it possible to these using MS Project server
and MS SharePoint services. Where will I get details to get started. Please
advice.

Thanks

Jibu

Jibu,
You will probably get a better response if you repost on the server
newsgroup. This newsgroup is dedicated to standalone desktop
installations of Project. You can find the server newsgroup at:
microsoft.public.project.server.

John
Project MVP
 
J

Jik

Thanks John.

Jibu

John said:
Jibu,
You will probably get a better response if you repost on the server
newsgroup. This newsgroup is dedicated to standalone desktop
installations of Project. You can find the server newsgroup at:
microsoft.public.project.server.

John
Project MVP
 
A

AM

Hey;

We are traking progress against % completes. So we decided to add a
column which would have Forecast % complete to the plan. This would
show us the deltas each week as to what was forecasted and where they
actually are (% complete).
But I realized there is no Forecast% complete in MS Project. Would
anyone help me how I could do this. Is there a way? Please advice.

Thanks
AM
 
J

John

AM said:
Hey;

We are traking progress against % completes. So we decided to add a
column which would have Forecast % complete to the plan. This would
show us the deltas each week as to what was forecasted and where they
actually are (% complete).
But I realized there is no Forecast% complete in MS Project. Would
anyone help me how I could do this. Is there a way? Please advice.

Thanks
AM

AM,
A single posting is all that is necessary.

John
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top