Project update and timesheet approval workflow

C

cam

Hi,

I just updated our project server 2003 to SP2. Now our timesheet approval
process seems to be dependent on the project update process.

Before applying SP2 (or SP1) we were able to approve timesheets separately
from the projects being updated. After SP2 we do not see any time to approve
until the project has been updated. After a resource submits their task
sheet for the week, the timesheet function will show all the tasks they
worked on, with zero hours. Once the PM updates a project we then see those
project hours appear on the timesheet for approval. The problem is we must
wait for all PMs to update their projects before we can get a complete
timesheet.

We would like to be able to see and approve all the timesheet hours
independently of the project updates. Can this be done? Did Prj Srv SP2
change the workflow of the project update and timesheet approval process?

Thanks!
 