Project Updates not appearing in time-sheets

  • Thread starter Tom Eckels, PMP
  • Start date
T

Tom Eckels, PMP

1. Project Is saved; when saved it publishes all changes;

2. Team members go into their current tasks and update % work complete;
when updated, they click update all to send the project manager their updates

3. Project manager goes into updates and accepts the updates;

4. When opening the project in either Project Web Access or in Microsoft
Project professional, a task looks like it is 100% complete

5. When the team member goes into their task-list it shows the task as
incomplete

6.the problem seems to be intermittent; some users are experiencing, and
others are able to successfully update their tasks

Our Environment:
Some users on windows 2000; others on Windows XP

Problem occurs regardless of the OS and version of Internet Explorer

Sites are set up in trusted zone; trusted zone ‘completely open’ or at
default ‘low’ level

Service pack 2 for Microsoft project server 2003 have been applied

All windows critical updates to the windows OS have been applied to the
server;
 
S

Scott m Wagner - EPM Consulting Services

Tom,

I may be wrong but I believe this is due to step 3 below.

When the PM goes into project and accepts the changes in Project Pro they
need to publish the updates.

Hope that helps :)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top