B
Brian
I have a fairly large Project file that I am working with (approx. 5000
lines) with a few hundred lines of LOE activities (these tasks are flagged in
a flag column "LOE" as 'Yes'). I am looking to use the existing project
Critical Path Functionality to identify where my actual critical tasks are.
The issue is that the LOE activities jump on the Critical path due to their
duration (most span the entire program).
My question is:
Can I override the total slack column to where LOE = Yes set Total Slack to
1 day, and have it recalculate for the remainder of the file?
Is there another way to calculate the critical path without deleting my LOE
tasks from the file and then using the critical path filter?
Thanks in advance,
Brian
lines) with a few hundred lines of LOE activities (these tasks are flagged in
a flag column "LOE" as 'Yes'). I am looking to use the existing project
Critical Path Functionality to identify where my actual critical tasks are.
The issue is that the LOE activities jump on the Critical path due to their
duration (most span the entire program).
My question is:
Can I override the total slack column to where LOE = Yes set Total Slack to
1 day, and have it recalculate for the remainder of the file?
Is there another way to calculate the critical path without deleting my LOE
tasks from the file and then using the critical path filter?
Thanks in advance,
Brian