P
Paul Linscott
Hi,
In PWA 2003, I created a project view table=task. When I look at a project
using this view, I only see the data/cost from actual resources. The
data/costs from generic resources are not included. Is there a way to also
include the generic data as well?
thanks
Paul
In PWA 2003, I created a project view table=task. When I look at a project
using this view, I only see the data/cost from actual resources. The
data/costs from generic resources are not included. Is there a way to also
include the generic data as well?
thanks
Paul