Project view

P

Paul Linscott

Hi,

In PWA 2003, I created a project view table=task. When I look at a project
using this view, I only see the data/cost from actual resources. The
data/costs from generic resources are not included. Is there a way to also
include the generic data as well?

thanks

Paul
 
D

Dale Howard [MVP]

Paul --

Out of curiosity, did you specify a Standard Rate for your Generic resources
in the Enterprise Resource Pool? I created a project and assigned only
generic resources to the tasks, and I can see the correct costs for each
task just fine in the Tasks Cost view in PWA. Let us know.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the books on Project Server"
 
P

Paul Linscott

Yes, the rate has been inserted. The problem appears to be resolved. It
appears there was a coordination problem between the resource manager, PM and
user. Neither one wants to take ownership of the problem. I think the
resource manager applied a 0 rate after the user printed the report, so the
printed report had the cost, but the view and project plan did not.

thx Dale
 