Project Web Access Gant Timescale

D

DOE/PMO

I'd like to change the Gant Timescale in PWA, project. The default is
weekly, but I need a monthly timescale for the Executive View of
Projects. How can I change the Timescale?
 
D

DOE/PMO

Sorry, Rick. Why do I not know which icon you are referring to? Where
is it? Please note that I am not referring to an individual project,
but rather on the Project Center. Thanks.
 
D

Dale Howard [MVP]

DOE/PMO --

I believe Rick is referring to the Zoom In and Zoom Out buttons on the
toolbar immediately above the Project Center data grid. Hope this helps.
 
A

A Nugraha

Dear Dale,

And how to change the bottom tier to week number? because the result of Zoom
In / Out only show as Quaterly or start date in Week.

Kindly need your advise.

Thanks in advanced,

A Nugraha
 
A

A Nugraha

in another word, in PWA we can't modify the timescale. And its limitation on
PWA to accomodate flexibility on changing Gantt timescale as not flexible as
project can do. :eek:(

Thanks anyway for your answer.
 