Project Web Access Gantt differs from Project Professional Gantt

S

Sean Stenlund

Please HELP,

The time-phased "actual work" and "protected actual work" are exactly the
same. Everything has published sucessfully. All actual work data is only
through the second week of July. The gantt in Project Professional has a
progress line on all tasks only to the second week in July. However, in PWA
the progress line extends out to any scheduled splits. This is occurring on
any tasks with splits in any project. Basically, it doesn't matter how far
in the future the planned split is, the progress line in Project Web Access
goes to the last split. Project Professional looks great.

I created a new task in one of the projects and updated the actual work day
by day to the second week of July, published, saved, looked at it in PWA, and
it is fine. As soon as I create the split and publish, the progress line
goes to the split.

Going crazy,

Sean Stenlund
 