AnneO
I am trying to run my resource reports tracking the start and end time of
those resources by week, month and year.
What I am finding is that I can put in my fixed duration with calendar for
calculations so that I can run through a 7 day week, when I view this data in
Project and in PWA Event Schedules the dates are correct. However, when I
run the data through the Resource Reports I am unable to return those same
dates. It appears that any project that begins or ends on a Saturday or
Sunday is truncated.
Any help would be greatly appreciated.
Thanks.
Anne
those resources by week, month and year.
What I am finding is that I can put in my fixed duration with calendar for
calculations so that I can run through a 7 day week, when I view this data in
Project and in PWA Event Schedules the dates are correct. However, when I
run the data through the Resource Reports I am unable to return those same
dates. It appears that any project that begins or ends on a Saturday or
Sunday is truncated.
Any help would be greatly appreciated.
Thanks.
Anne