Project Web Access - Resource Reports Duration

A

AnneO

I am trying to run my resource reports tracking the start and end time of
those resources by week, month and year.

What I am finding is that I can put in my fixed duration with calendar for
calculations so that I can run through a 7 day week, when I view this data in
Project and in PWA Event Schedules the dates are correct. However, when I
run the data through the Resource Reports I am unable to return those same
dates. It appears that any project that begins or ends on a Saturday or
Sunday is truncated.

Any help would be greatly appreciated.

Thanks.

Anne
 
M

Mike Glen

Hi Anne,

Ditto:
Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 