Hello,
We have just installed Microsoft Project Server 2003 to track time on our
University Project and I have published the plan to the Server and all is
working fine...until I receive time updates from resources.
Our week is set to Start on Friday, and we are using Non-Managed Periods
with Timesheet disabled.
When a resource enters time a task update is sent to me but I cannot see all
the hours they enter.
For example, a resource may submit the following time:
F S S M T W T
2 1 1 1 2
But i will only see
F S S M T W T
1 2
However, when I go to Adjust Actuals under the 'Resources' tab I can see all
the hours they've entered, and when I click Update All under Task Updates it
updates correctly. Just I can't see all the hours in the Update view!
Has anyone else had this problem? Any ideas would be greatly appreciated!!!
Cheers
R
We have just installed Microsoft Project Server 2003 to track time on our
University Project and I have published the plan to the Server and all is
working fine...until I receive time updates from resources.
Our week is set to Start on Friday, and we are using Non-Managed Periods
with Timesheet disabled.
When a resource enters time a task update is sent to me but I cannot see all
the hours they enter.
For example, a resource may submit the following time:
F S S M T W T
2 1 1 1 2
But i will only see
F S S M T W T
1 2
However, when I go to Adjust Actuals under the 'Resources' tab I can see all
the hours they've entered, and when I click Update All under Task Updates it
updates correctly. Just I can't see all the hours in the Update view!
Has anyone else had this problem? Any ideas would be greatly appreciated!!!
Cheers
R