Project Web Access Task / WBS Display

T

TomCervenka

I'm trying to use Project Web Access to manage detailed Work Breakdown
Structures (Task lists) for my company. I've entered the WBS into a Project
File but never entered any durations for the tasks as the process is more
centered on performing one step after another or several steps at the same
time, not necessarily tied to a Calendar or set number of days. When I
publish the project onto web server, the resource sees every task that's in
their queue, regardless if it is to be done now. For example, say a four
step process requires them to do Task A, then Task B, then Task C, then Task
D. I don't want them to see Task B until Task A is 100% Complete. Any ideas?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top