Project Web Access Tasks not updated

I

Inger

Couple of questions from newish user:

I modified the start date of my project in MS Project 2003 and rebulished
the information to Project Server. I see the start date gets modified in the
Project Center, but not in the Timesheet view under Tasks in Project Web
Access. Howcome?

I extended the duration of a task in MS Project. I rebublished it to Project
Server and filled in hours in the Timesheet in Project Web Access. However,
when pulling the Project Server information back into MS Project,
(Collaborate->Update Project Progress), the percent complete does not get
updated on the Gantt chart or in the Task Information for the two tasks with
modified duration. However, when I run a report of actual work, the hours are
reflected. Howcome?

Regards,
Inger M. Knudsen
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top