I
Inger
Couple of questions from newish user:
I modified the start date of my project in MS Project 2003 and rebulished
the information to Project Server. I see the start date gets modified in the
Project Center, but not in the Timesheet view under Tasks in Project Web
Access. Howcome?
I extended the duration of a task in MS Project. I rebublished it to Project
Server and filled in hours in the Timesheet in Project Web Access. However,
when pulling the Project Server information back into MS Project,
(Collaborate->Update Project Progress), the percent complete does not get
updated on the Gantt chart or in the Task Information for the two tasks with
modified duration. However, when I run a report of actual work, the hours are
reflected. Howcome?
Regards,
Inger M. Knudsen
I modified the start date of my project in MS Project 2003 and rebulished
the information to Project Server. I see the start date gets modified in the
Project Center, but not in the Timesheet view under Tasks in Project Web
Access. Howcome?
I extended the duration of a task in MS Project. I rebublished it to Project
Server and filled in hours in the Timesheet in Project Web Access. However,
when pulling the Project Server information back into MS Project,
(Collaborate->Update Project Progress), the percent complete does not get
updated on the Gantt chart or in the Task Information for the two tasks with
modified duration. However, when I run a report of actual work, the hours are
reflected. Howcome?
Regards,
Inger M. Knudsen