Project Web Access Views

W

Will C.

Is there any way to be able to select custom views while in Project Web
Access? Or are the views they list the only views you get (Assignments Cost
- Tasks Work)?

I am unable to select any of the views i have created in the MSP 2007 file
while accessing the file through Project Web Access
 
D

Dale Howard [MVP]

Will C --

Custom Views for Project Professional 2007 are only available in that
software application. You cannot see them in PWA. Hope this helps.
 
W

Will C.

The weird thing is that it looks like there is one view in the PWA that is
NOT standard. I can see one view with a "_" before it, and that is how we
designate our custom views. Is there any possible way a Sharepoint admin was
able to create this view somehow? Any idea where it may have come from?

Every other view are the standard Assignments and Tasks views in the drop
down.
 
D

Dale Howard [MVP]

Will C --

Anyone who is a member of the Administrators group in Project Server 2007
can create a custom View in PWA. I can state from experience that using the
underscore character to precede the name of a custom View in PWA is a very
helpful way to make custom Views stand out on the list. I have no idea
where that View may have originated. Hope this helps.
 