A
Athena
Hello,
I have been trying to create a project with the following outline:
4/12 4/14 4/16 4/18
..........................
1 Task1 1 1 1 1 ................
2 Task2 1 1 1 .................
3 Task3 1 1 1 ..................
....
In each case the tasks run at several day intervals only for one day.
They are all completed in 34 days.
I also would like to place some numbers within the tasks bars.
I am using Project 2000.
How can I do this? Thank you.
Athena
I have been trying to create a project with the following outline:
4/12 4/14 4/16 4/18
..........................
1 Task1 1 1 1 1 ................
2 Task2 1 1 1 .................
3 Task3 1 1 1 ..................
....
In each case the tasks run at several day intervals only for one day.
They are all completed in 34 days.
I also would like to place some numbers within the tasks bars.
I am using Project 2000.
How can I do this? Thank you.
Athena