I'm using project pro 2003. I have developed a schedule for a project that will be used in two different portions of the organization. One portion is using the server. I have to set up the resource sheet differently for each department. I cna't get them to use one sheet for the project, no avail. Their output reporting is differently
So my question is how can use one project with two different resources? Or do i have to maintain two project schedules with two different resource sheets
So my question is how can use one project with two different resources? Or do i have to maintain two project schedules with two different resource sheets