K
kmadore
We have a problem with permissions being pushed to the Project Workspace when
a task is delegated to an individual who is not a team member on the project
schedule. The team member is in the global resource pool. The project
manager accepts the update for the delegated task and is prompted to replace
the local resource with the enterprise resource. Question 1: why doesn't
project server recognize that this resource is in the global resource pool
rather than putting the person in the schedule as a local resource?
After the PM accepts the update and goes to Publish | Collaborate | All
Information. The new resource does not get pushed to the WSS Workspace when
the project is published. The only way to get the resource added to the site
permissions is for the Admin to go into the Manage SharePoint Sites and
synchronize the permissions. Question 2: Why isn't the permission for the
new resource on the task pushed to the project workspace? What step is
missing to have this happen?
In all other scenarios the resource permissions are pushed to the workspace
when the project is published.
We are using Project Server 2003 and WSS 2.0.
a task is delegated to an individual who is not a team member on the project
schedule. The team member is in the global resource pool. The project
manager accepts the update for the delegated task and is prompted to replace
the local resource with the enterprise resource. Question 1: why doesn't
project server recognize that this resource is in the global resource pool
rather than putting the person in the schedule as a local resource?
After the PM accepts the update and goes to Publish | Collaborate | All
Information. The new resource does not get pushed to the WSS Workspace when
the project is published. The only way to get the resource added to the site
permissions is for the Admin to go into the Manage SharePoint Sites and
synchronize the permissions. Question 2: Why isn't the permission for the
new resource on the task pushed to the project workspace? What step is
missing to have this happen?
In all other scenarios the resource permissions are pushed to the workspace
when the project is published.
We are using Project Server 2003 and WSS 2.0.