Project Zero Line

B

burtjk

How does one get the project zero line to populate the baseline cost and
variance fields without using project options calculate now?
 
D

Dale Howard [MVP]

burtjk --

This is automatic when you click Tools - Tracking - Save Baseline. Hope
this helps.
 