T
Tommy T.
As an OEM, most of my projects are production plans. Most of the tasks
within the plan are building the subassemblies that make up the final
product. Subtasks to these subassemblies are ordering and recieving all
parts necessary to build the unit.
When entering a new project, all the tasks go in initially with an estimated
duration of 1 day. I get a report from purchasing which details the purchase
orders and due dates for the parts. I would like to use the latest due date
as a worst case for the finish date of the 'All parts Received' task.
However, when I enter the finish date into the task, the start date then
slides down the calendar to maintain a 1 day duration. I then have to go
back in and reenter the start date which then calculates the task duraiton
correctly. I have to go in a third time and uncheck the 'estimated' check
box to get rid of the nasty question marks throughout the plan.
What am I missing? Is there any way to maintain the task start date and
enter a finish date and have the program calculate task duration without
having to go onto the task informaiton dialog multiple times per task?
Any help is appreciated,
Tom T.
within the plan are building the subassemblies that make up the final
product. Subtasks to these subassemblies are ordering and recieving all
parts necessary to build the unit.
When entering a new project, all the tasks go in initially with an estimated
duration of 1 day. I get a report from purchasing which details the purchase
orders and due dates for the parts. I would like to use the latest due date
as a worst case for the finish date of the 'All parts Received' task.
However, when I enter the finish date into the task, the start date then
slides down the calendar to maintain a 1 day duration. I then have to go
back in and reenter the start date which then calculates the task duraiton
correctly. I have to go in a third time and uncheck the 'estimated' check
box to get rid of the nasty question marks throughout the plan.
What am I missing? Is there any way to maintain the task start date and
enter a finish date and have the program calculate task duration without
having to go onto the task informaiton dialog multiple times per task?
Any help is appreciated,
Tom T.