Hi
A question about Project Server 2007
When resources go to 'Add Lines' in their timesheets, they see projects
where they are members of the resource pool and they see tasks on which they
have been assigned work. Closing tasks to updates removes the tasks from
this 'Add Lines' feature on the timesheets but the list of projects still
remains. How can I remove projects from this 'Add Lines' list once the
project is complete?
I've tried making sure that all tasks are complete (the project shows as
100% Complete), all tasks are closed to updates but when I open a timesheet
for a period after the end of the project, the project still appears when I
go to 'Add Lines'. In a year or so resources will have an enormous number of
projects in this list if I can't hide old projects.
I assume I'm missing something, can someone help me with this?
Thanks in advance.
Andy
A question about Project Server 2007
When resources go to 'Add Lines' in their timesheets, they see projects
where they are members of the resource pool and they see tasks on which they
have been assigned work. Closing tasks to updates removes the tasks from
this 'Add Lines' feature on the timesheets but the list of projects still
remains. How can I remove projects from this 'Add Lines' list once the
project is complete?
I've tried making sure that all tasks are complete (the project shows as
100% Complete), all tasks are closed to updates but when I open a timesheet
for a period after the end of the project, the project still appears when I
go to 'Add Lines'. In a year or so resources will have an enormous number of
projects in this list if I can't hide old projects.
I assume I'm missing something, can someone help me with this?
Thanks in advance.
Andy