Projects become unlinked from the resource pool

J

Jack

Hello;
I have a question about resource pools and multiple projects. I have MS
Project 2002 and have all of my designers using this tool as well as all
supervisors and managers.
I have the system administrator create a location on the server for my
resource pool and another directory for all the projects. The directory for
the resource pool only has me with modify permissions and everyone else who
has to use the pool as read only.
I have a laptop and work out of two offices.
When I work in one office during the week, I don't have issues with the
resource pool or projects, when i go to another office for work, i end up
having problems with the resource pool.
Just today, before lunch, i had the resource pool open and everything was
linked properly, i left for lunch and came back and noticed that all the
projects are now unlinked and the only projects that are linked are two that
I have not touch for many years.
Any idea what would cause this and how do i relink the projects? Is there
an automated way or do i have to relink them individually?
let me know.

(e-mail address removed)
 