J
James
We're currently trying to use Project in an environment that is very
deadline-driven. Our end dates for a project are sacred. This makes it
difficult to work with Project (which would probably otherwise be perfect
for our needs) because I can't seem to convince it to lock in the end date.
It always "helpfully" shifts it around when the scope of the project
changes.
I've tried every combination of settings, options, etc., that I can come up
with, but haven't found the magic combo. I can't tell you how many times
I've set a task to "Must Finish On" a certain constraint date, and then had
project move it around anyway. It's making me mental.
Here's what we're trying to do:
At the beginning of a project, I want to specify the estimated number of
work hours, estimated resources, and a firm end date.
Before a project starts, or during the project, the scope may change. I
want this to change the START DATE, not the end date. If the start date is
too early, I would then know that I need to allocate more resources to it
until the start date comes into line. The start date should move where it
needs to in order to fit the work and the resources, but under no
circumstances would I ever want the finish date to change unless I
explicitly change it.
I know there's got to be a magic combination of options that makes this all
come together, but I haven't been able to find it.
Anyone have any suggestions?
Thanks in advance,
James
deadline-driven. Our end dates for a project are sacred. This makes it
difficult to work with Project (which would probably otherwise be perfect
for our needs) because I can't seem to convince it to lock in the end date.
It always "helpfully" shifts it around when the scope of the project
changes.
I've tried every combination of settings, options, etc., that I can come up
with, but haven't found the magic combo. I can't tell you how many times
I've set a task to "Must Finish On" a certain constraint date, and then had
project move it around anyway. It's making me mental.
Here's what we're trying to do:
At the beginning of a project, I want to specify the estimated number of
work hours, estimated resources, and a firm end date.
Before a project starts, or during the project, the scope may change. I
want this to change the START DATE, not the end date. If the start date is
too early, I would then know that I need to allocate more resources to it
until the start date comes into line. The start date should move where it
needs to in order to fit the work and the resources, but under no
circumstances would I ever want the finish date to change unless I
explicitly change it.
I know there's got to be a magic combination of options that makes this all
come together, but I haven't been able to find it.
Anyone have any suggestions?
Thanks in advance,
James