D
David F-H
We are using MS Project Server 2007 (SP1) / SQL Server 2005. One of the
problems that we experienced prior to SP1 was tasks appearing at wrong levels
or out of order when plans were closed and subsequently re-opened. Since we
have
installed SP1 this appears to be behaving better, with the following
exception:
I have imported a project plan (.mpp) into Project Server and have found
that a couple of the tasks have not imported correctly. The interesting thing
is, however, that the tasks are correct when viewed in PWA / Project Center,
but incorrect when opened in MS Project Professional. I have tried clearing
the cache and deleting the 12 and cache folders (as it appeared to me to be a
caching problem), but this made no difference.
The tasks appear in PWA correctly as :
....
Project Management (level 3 summary task)
Customer Project Manager (level 4 detail task)
Internal Project manager (level 4 detail task)
Kick off Meeting (level 3 detail task)
Sign Contract (level 3 detail task)
but look like this in Project Professional :
Project Management (level 3 summary task)
Customer Project Manager (level 4 detail task)
Internal Project manager (level 4 summary task)
Kick off Meeting (level 5 detail task)
Sign Contract (level 3 detail task)
We can fix by changing the plan in Project Professional to be correct, but
would like to know if there is a better fix that can be applied? If not,
then this does not instil confidence in the import process for us.
We also have another (low impact) problem reported by the users of one
project where blank lines appear to be rearranged when they go back into a
project in MS Project Prof (though the actual tasks are OK and in correct
order).
problems that we experienced prior to SP1 was tasks appearing at wrong levels
or out of order when plans were closed and subsequently re-opened. Since we
have
installed SP1 this appears to be behaving better, with the following
exception:
I have imported a project plan (.mpp) into Project Server and have found
that a couple of the tasks have not imported correctly. The interesting thing
is, however, that the tasks are correct when viewed in PWA / Project Center,
but incorrect when opened in MS Project Professional. I have tried clearing
the cache and deleting the 12 and cache folders (as it appeared to me to be a
caching problem), but this made no difference.
The tasks appear in PWA correctly as :
....
Project Management (level 3 summary task)
Customer Project Manager (level 4 detail task)
Internal Project manager (level 4 detail task)
Kick off Meeting (level 3 detail task)
Sign Contract (level 3 detail task)
but look like this in Project Professional :
Project Management (level 3 summary task)
Customer Project Manager (level 4 detail task)
Internal Project manager (level 4 summary task)
Kick off Meeting (level 5 detail task)
Sign Contract (level 3 detail task)
We can fix by changing the plan in Project Professional to be correct, but
would like to know if there is a better fix that can be applied? If not,
then this does not instil confidence in the import process for us.
We also have another (low impact) problem reported by the users of one
project where blank lines appear to be rearranged when they go back into a
project in MS Project Prof (though the actual tasks are OK and in correct
order).