C
Christina Odom
This issue came up on Friday and I still haven't been able to track it
down. Several projects were made via Project Pro and have been worked
on for a couple of weeks. The clients used to create and modify the
projects have all be pre-SP1. Last week, a couple of PM's updated
their Project Professional with SP1 and then proceded to make updates
to several projects. These PMs are having issue with saving &
checking in these projects they've edited. In my (pre-sp1) Project
Pro client, I'm able to create, check in, check out and modify a new
project no problem. However, when I save one of the SP1 modified
projects and attempt to save it to MOPS as a new project, MOPS throws
a generic error stating to contact system admin (no error message is
in the details). The queue does not have a failed job, however there
are several jobs that have been marked "Send Incomplete".
Has anyone come across this?
down. Several projects were made via Project Pro and have been worked
on for a couple of weeks. The clients used to create and modify the
projects have all be pre-SP1. Last week, a couple of PM's updated
their Project Professional with SP1 and then proceded to make updates
to several projects. These PMs are having issue with saving &
checking in these projects they've edited. In my (pre-sp1) Project
Pro client, I'm able to create, check in, check out and modify a new
project no problem. However, when I save one of the SP1 modified
projects and attempt to save it to MOPS as a new project, MOPS throws
a generic error stating to contact system admin (no error message is
in the details). The queue does not have a failed job, however there
are several jobs that have been marked "Send Incomplete".
Has anyone come across this?