J
Javier
I have a program in MS 2003 with 50 individual projects all in the same file
as they share resources. One of the projects has been cancelled but some of
the tasks were already completed. This cancelled project has no dependencies
with other projects and I want to know what is the best way to reflect this
situation in MS Project. I can think of deleting the not completed tasks or
make them 100% complete but this will not reflect the original plan or the
reality. Any suggestion?
Thanks and regards
as they share resources. One of the projects has been cancelled but some of
the tasks were already completed. This cancelled project has no dependencies
with other projects and I want to know what is the best way to reflect this
situation in MS Project. I can think of deleting the not completed tasks or
make them 100% complete but this will not reflect the original plan or the
reality. Any suggestion?
Thanks and regards